Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2013 |
Basis
Engineering
|
Rosetti
Marino |
INAgip d.o.o. |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
IKA
Field - IKA JZ EPC and
IKA A revamping
|
 |
Activity Description |
Development
of detail engineering instruments project literature, for both IKA Field
platforms, for
almost the majority of field instruments as follow:
specialized instrumentation
- Data
Sheet, Inspection
D.S., M.R., R.D.D.S.
& T.B.E.
for Choke Valve;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
Well Wing Valve;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
ESD Ball Valve;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
BDV Gate Valves;
- Data
Sheet, Inspection
D.S.,
M.R., R.D.D.S.
& T.B.E.
for Liquid Discharge
Valve;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
Valve Local Panels;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
Safety Valves;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
Regulating Valves;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for Orifice Plates;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
Temperature
& Pressure Transmitters;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S.
& T.B.E.
for
Pressure & Level Switches;
- Data
Sheet, Inspection D.S.,
M.R., R.D.D.S. & T.B.E.
for Pig Signallers.

Such
activities have been surrounded by an internal auditing system,
for which Comments
Sheets
have been issued by a third party, against the first draft of each
document: written replies and clarifications to such comments have
been provided.

Repeated meetings with Vendors for the alignement of their bids under the T.B.E. (Technical Bid Evaluation) process at Client's premises have been also performed. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2012 |
Basis
Engineering
|
Rosetti
Marino |
Foxtrot - Mustang |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Marlin
Field Development
|
 |
Activity Description |
Complete and detailed Tender literature
endorsement for all the Telecommunication discipline implied aspects, including the
applicable Companyand
project standards and specifications. As a final result, a written
report have been prepared, quoting in detail all the detected
deviations, discrepancies, and inconsistencies, including the
evaluation of such requirements against the applied and the applicable
international standards as also commented as well. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2012 |
Basis
Engineering
|
Rosetti
Marino |
Total E&P UK |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
West
Franklin and
Elgin B platforms (North
Sea)
|
 |
Activity Description |
Development
of detail engineering instruments project literature, for both WFA & ELB
platforms, for
almost the majority of field instruments as follow:
specialized instrumentation
- Data
Sheet, Inspection
D.S., M.R. & R.D.D.S. for Nucleonic Levels;
- Data
Sheet, Inspection D.S., M.R. & R.D.D.S. for GWR Levels;
- Data
Sheet, Inspection D.S., M.R. & R.D.D.S. for Sand Detectors.
others activities
- Drawings preparation for the drums interested by the Nucleonic Level;
- Nucleonic Level kick-off meeting preparation

As a further additional project activity, a final detailed Gap Analysis for
both platforms have been
prepared (the Excel™ format report have been originated by the
bid's P&ID
comparison with the detailed engineering phase P&ID, in terms of removed, added and/or modified items), duly
filled with the required mark
ups (on each P&ID pair) and commnents as well. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2011 |
Basis
Engineering
|
Rosetti
Marino |
Total E&P UK |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
West
Franklin and
Elgin B platforms (North
Sea)
|
 |
Activity Description |
Complete Tender literature
endorsement for Instrument
& Control discipline implied aspects.
Additional endorsement for all the project literature related
to Telecommunication
discipline activities,
including the NESSCO's
preliminary bid evaluation as also the computation of a Gap Analysis (for
economical impacts 'punch
list'), originated by modified contractual requirements. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2011 |
Basis
Engineering
|
Rosetti
Marino |
Shell UK |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Clipper
PLQ Upgrade Project
|
 |
Activity Description |
Bid project documentation review for all the Instrument & Control
and Telecommunication
disciplines aspects, in order to carry out the Tender
qualification section preparation (in terms of congruity verification and
clarification requests for the Client's
supplied literature). |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2010-11 |
Basis
Engineering
|
Rosetti
Marino |
Agip KCO |
Italy |
 |
Industry |
Project |
Oil
& Gas - Midstream |
Kashagan
Pig Trap Skids Procurement
|
 |
Activity Description |
Technical Vendor's bids
evaluation for all skids actuated
valves including LCP
(Local Control Panels), pig detectors, pressure and temperature
transmitters, with
the next preparation of the related Data Sheets
revision
per order.
Hook
up drawings complete revision (primary & secondary
typical), including the consequent revision of the implied MTO
(Material Take Off).
MIAP
material codification assistance for all the revised and/or modified MTO's
parts/materials.
Instrument layout drawing revision (including piping layer),
for all skids.
Skids electrical layout drawings revision.
Large amount of project drawings revision, for the new consortium
logo (KCOI)
introduction, and the inclusion of appropriate fields for
the next russian translation process (bilingual texts). |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2010 |
Basis
Engineering
|
N.A. |
ENI Divisiona E&P |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Canonica d'Adda Feed
|
 |
Activity Description |
Development of instrumental engineering
for FEED,
performed both for specialized aspects, as also for required plant
installations documentation:
specialized instrumentation
- Data
Sheet, Inspection
D.S. and R.D.D.S.
for Choke Valve;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
Well Wing Valve;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
ESD Ball Valve;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
BDV Gate Valves;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
Valve Local Panels;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
Safety Valves;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for
Regulating Valves;
- Data
Sheet, Inspection
D.S. and
R.D.D.S. for Orifice Plates;
plant installations
- MTO arrangement for
instrumentation bulk
materials;
- Data
Sheet, Inspection
D.S. and
R.D.D.S.
for Communication and Instrumentation Cables;
- Data
Sheet, Inspection
D.S. and
R.D.D.S.
for Optical Fiber Cables;
- preliminary
for Fiber Optic Cables Laying Specification.
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2010 |
Basis
Engineering
|
Tecon |
Abu Qir Petroleum |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
ABU QIR - WAQ PI
Platform Revamping
|
 |
Activity Description |
CAD drafting of P&ID
retrieved directly from older existing paper format, due to absence of
similar documents in electronic format.
During the organization of the new digital master set,
however, have been duly implemented the layers definition for
main lines, secondary lines, equipments, etc. according to the
different thickness of plotter pens, as also for the used standard
simbols, as required by Client.
Obviously, were also incorporated comments and changes to P&ID, under
a new document revision, in compliance to the running activities of
the revamping project. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2010 |
Basis
Engineering
|
Rosetti
Marino |
Agip KCO |
Italy |
 |
Industry |
Project |
Oil
& Gas - Midstream |
Kashagan East Field Development (Test
Separator)
|
 |
Activity Description |
Changes and comments integrating activities
for drawings to be related to both, electrical and instrumentation
disciplines, as better listed herebelow:

-
Isometric
Tracing Sketches drawings revision for skid B4-200-XY-001 (Test
Separator);
- Loop
Diagrams drawings revision for skid B4-200-XY-001 (Test
Separator);
- Wiring
Diagrams drawings revision for skid
B4-200-XY-001 (Test Separator). |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2009-10 |
Basis
Engineering
|
Rosetti
Marino |
Agip KCO |
Italy |
 |
Industry |
Project |
Oil
& Gas - Midstream |
Kashagan Pig Trap
Skids (AKCO - EPC2, EPC3, EPC4)
|
 |
Activity Description |
Development of detailed instrumental
engineering (document drafting and subsequent revisions), performed
both for specialized aspects, as also for required plant installations
documentation:
specialized instrumentation
- Supply
Specification per Actuated Valves and Valves Local Panels;
- Data
Sheet, Inspection
D.S. for ESV Actuated Valves;
- Data Sheet,
Inspection
D.S. for ESV Actuated
Valves Local Panels;
- Data Sheet,
Inspection
D.S. for Electrically Operated HS
Valves (MOV);
- Data Sheet, Inspection
D.S. e Supply
Specification for Pressure Transmitters;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Temperature Transmitters;
- Data Sheet, Inspection
D.S. e Supply
Specification for Flow Transmitters;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Orifices Plates;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Pressure Gauges;
-
Instrument List drafting and revision;
-
Valves List drafting and
revision;
plant installations
-
instrumentation bulk materials MTO;
-
Primary
and Secondary Hook-up
for Instrumentation;
- Electrical Hook-up for
Instrumentation;
-
Instruments
and Junction Boxes Layout;
-
Instrument Junction Boxes Terminations
drafting
and revision;
- Instrument Junction Boxes Rack Layout drafting
and revision;
- Instrument
and Air Distribution
Layout drafting;
- Instrumentation Cable Block
Diagrams revision;
-
Instrumentation Cable
List drafting
and revision;
-
Instrumentation Cable Routing Layout drafting
and revision;
-
Instrumentation Cables Technical Data
Sheet drafting
and revision;
-
Instrumentation Cable Tray Technical
Data Sheet drafting
and revision;
electrical, others
-
electrical materials MTO drafting
and revision;
- Electrical Cables Routing Layout revision;
-
instrumentation and electrical materials MIAP system
codification.
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2009 |
Eurotherm
|
Snamprogetti
|
Sonatrach |
Italy |
 |
Industry |
Project |
Oil
& Gas - Midstream |
Oleoduc LZ2 24” GPL Hassi
R’Mel – Arzew
|
 |
Activity Description |
Translation from Italian to French of the
following documents, verifying the congruity for its contents, related
to Invensys's
control system:
- Functional
Design Specification;Oleoduc
LZ2 24” GPL Hassi R’Mel – Arzew
- Control System Operator Personnel Training
Course (Vendor premises);
- Control System Operator Personnel Training
Course (on
site);
-
Inspections and Tests Plan;
- FAT
- Factory Acceptance Tests
- Project Organization Chart;
Translation
from English to French of the following documents:
-
Project
Execution Plan.
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2008-09 |
Basis
Engineering
|
Saipem
Sa / Rosetti M. |
Total E&P
Congo |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Libondo
LBD1
Platform
|
 |
Activity Description |
Hazop session
presence for the identification and assessment of risks
related to
security and continuity of the plant management system, with respect to
measurement and control solutions adopted (and the associated
instrumentation used), performed in conjunction with the other involved
disciplines.
Meetings
with
Final Customer for checking the document progress and for the correct
definition of the I/O List and the other aspects related to the ICSS
Control System (Infautelec).
Development
of detailed instrumental
engineering (document drafting and subsequent revisions),
as here below listed:

- I/O List
drafting and revision (arranged as per Control System ICSS's format);
-
Instrument
List revision;
- Technical
Specification
and R.D.D.S.
for Motorized Choke
Valves;
- Data
Sheet, Inspection
D.S. for Motorized
Choke Valves;
- Technical Specification and
R.D.D.S. for
XV
On-Off Valves;
- Data
Sheet, Inspection
D.S. for XV
On-Off
Valves;
- Technical Specification and
R.D.D.S. for
Hydraulic
ESD
On-Off
Valves;
- Data
Sheet, Inspection
D.S. for Hydraulic
ESD On-Off
Valves;
- Technical Specification and
R.D.D.S. for
Control Valves;
- Data
Sheet, Inspection
D.S. for Control Valves;
- Technical Specification and
R.D.D.S. for
Press.
& Temp. Safety
Valves;
- Data
Sheet, Inspection
D.S. for Press.
& Temp. Safety Valves;
- Technical Specification and
R.D.D.S. for
Pig
Detector and Indicator;
- Data
Sheet, Inspection
D.S. for Pig
Detector and Indicator;
- Technical Specification
and R.D.D.S. for
Pressure Transmitters;
- Data
Sheet, Inspection
D.S. for Pressure
Transmitters;
- Technical Specification and
R.D.D.S. for
Differential
Press. Transmitters;
- Data
Sheet, Inspection
D.S. for
Differential
Pressure Transmitters;
- Technical Specification and
R.D.D.S. for
Temperature
Transmitters;
- Data
Sheet, Inspection
D.S. for Temperature
Transmitters;
- Technical
Specification and
R.D.D.S. for Level
Transmitters;
- Data
Sheet, Inspection
D.S. for Level
Transmitters;
- Technical
Specification and
R.D.D.S. for Differential
Pressure Gauges;
- Data
Sheet, Inspection
D.S. for Differential
Pressure Gauges;
-
Technical
Specification and
R.D.D.S. for Press.
& Temper. Gauges;
- Data
Sheet, Inspection
D.S. for Pressure & Temperature
Gauges;
- Technical
Specification and
R.D.D.S. for Level
Gauges;
- Data
Sheet, Inspection
D.S. for Level
Gauges;
- Technical
Specification and
R.D.D.S. for Pressure,
Temperature & Level Switches;
- Data
Sheet, Inspection
D.S. for Pressure, Temperature
& Level
Switches;
- Technical
Specification and
R.D.D.S. for Restriction
Orifices;
- Data
Sheet, Inspection
D.S. for Restriction
Orifices;
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2008 |
Basis
Engineering
|
Rosetti
Marino |
Edina (Edison/INA) |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Izabela
North e South
Platforms
|
 |
Activity Description |
Development
of detailed instrumental
engineering (document drafting and subsequent two revisions), as follow:

documents related to Izabela North


- Technical
Specification e
R.D.D.S. per Actuated
Valves (SDV & BDV);
- Data
Sheet, Inspection
D.S. per Actuated
Valves (SDV & BDV);
- Technical Specification
e R.D.D.S.
per Choke Valves;
-
Data
Sheet, Inspection
D.S. per Choke Valves;
- Technical
Specification e
R.D.D.S. per Liquid
Discharge Valves;
- Data
Sheet, Inspection
D.S. per Liquid
DischargeValves;
- Technical Specification
e R.D.D.S.
per Valves
Local Control Panels;
- Data
Sheet, Inspection
D.S. per Valves
Local Control Panels;
- Technical
Specification e
R.D.D.S. per Orifice
Plates;
- Data
Sheet, Inspection
D.S. per Orifice Plates;
- Technical Specification
e R.D.D.S.
per F&G Field
Devices;
-
Data
Sheet, Inspection
D.S. per F&G
Field Devices;
- Technical
Specification e
R.D.D.S. per Multivariable
Transmitter;
- Data
Sheet, Inspection
D.S. per Multivariable
Transmitter;
-
Technical
Specification e
R.D.D.S. per Pressure Transmitters;
-
Data
Sheet, Inspection
D.S. per Pressure
Transmitters;
- Technical
Specification
e R.D.D.S.
per Differential Press. Transmitters;
-
Data
Sheet, Inspection
D.S. per Differential
Pressure Transmitters;
-
Technical
Specification e
R.D.D.S. per Level
Switches;
-
Data
Sheet, Inspection
D.S. per Level Switches;
- Technical Specification
e R.D.D.S.
per Flow Switches;
-
Data
Sheet, Inspection
D.S. per Flow
Switches;
- Technical
Specification
e R.D.D.S.
per Pressure Switches;
- Data
Sheet, Inspection
D.S. per Pressure
Switches;
- Technical
Specification
e R.D.D.S.
per Level Glass;
-
Data
Sheet, Inspection
D.S. per Level Glass;
- Technical
Specification
e R.D.D.S.
per Pressure. Gauges;
-
Data
Sheet, Inspection
D.S. per Pressure Gauges;
- Technical
Specification e
R.D.D.S. per Temperature Gauges;
-
Data
Sheet, Inspection
D.S. per Temperature
Gauges;
- Technical
Specification
e R.D.D.S.
per Safety
Valves;
-
Data
Sheet, Inspection
D.S. per Safety
Valves;
- Technical Specification
e R.D.D.S.
per Self RegulatingValves;
-
Data
Sheet, Inspection
D.S. per Self
Regulating Valves;
- Technical
Specification
e R.D.D.S.
per Sand Detector;
-
Data
Sheet, Inspection
D.S. per Sand Detector;
- Technical
Specific. e
R.D.D.S. for Fiscal Flow Measurement Daniel
Senior;
- Data
Sheet, Inspection
D.S. for Fiscal
Flow Measurement Daniel
Senior;
- Technical
Specification
e R.D.D.S. for Ultrasound Fiscal Flow Measurement;
- Data
Sheet, Inspection
D.S. or
Ultrasound Fiscal Flow Measurement;

documents related to Izabela South


- Technical
Specification e
R.D.D.S. per Actuated
Valves (SDV & BDV);
- Data
Sheet, Inspection
D.S. per Actuated
Valves (SDV & BDV);
- Technical Specification
e R.D.D.S.
per Choke Valves;
-
Data
Sheet, Inspection
D.S. per Choke Valves;
- Technical
Specification e
R.D.D.S. per Liquid
Discharge Valves;
- Data
Sheet, Inspection
D.S. per Liquid
DischargeValves;
- Technical Specification
e R.D.D.S.
per Valves
Local Control Panels;
- Data
Sheet, Inspection
D.S. per Valves
Local Control Panels;
- Technical
Specification e
R.D.D.S. per Orifice
Plates;
- Data
Sheet, Inspection
D.S. per Orifice Plates;
- Technical Specification
e R.D.D.S.
per F&G Field
Devices;
-
Data
Sheet, Inspection
D.S. per F&G
Field Devices;
- Technical
Specification e
R.D.D.S. per Multivariable
Transmitter;
- Data
Sheet, Inspection
D.S. per Multivariable
Transmitter;
-
Technical
Specification e
R.D.D.S. per Pressure Transmitters;
-
Data
Sheet, Inspection
D.S. per Pressure
Transmitters;
- Technical
Specification
e R.D.D.S.
per Differential Press. Transmitters;
-
Data
Sheet, Inspection
D.S. per Differential
Pressure Transmitters;
-
Technical
Specification e
R.D.D.S. per Level
Switches;
-
Data
Sheet, Inspection
D.S. per Level Switches;
- Technical Specification
e R.D.D.S.
per Flow Switches;
-
Data
Sheet, Inspection
D.S. per Flow
Switches;
- Technical
Specification
e R.D.D.S.
per Pressure Switches;
- Data
Sheet, Inspection
D.S. per Pressure
Switches;
- Technical
Specification
e R.D.D.S.
per Level Glass;
-
Data
Sheet, Inspection
D.S. per Level Glass;
- Technical
Specification
e R.D.D.S.
per Pressure. Gauges;
-
Data
Sheet, Inspection
D.S. per Pressure Gauges;
- Technical
Specification e
R.D.D.S. per Temperature Gauges;
-
Data
Sheet, Inspection
D.S. per Temperature
Gauges;
- Technical
Specification
e R.D.D.S.
per Safety
Valves;
-
Data
Sheet, Inspection
D.S. per Safety
Valves;
- Technical Specification
e R.D.D.S.
per Self RegulatingValves;
-
Data
Sheet, Inspection
D.S. per Self
Regulating Valves;
- Technical
Specification
e R.D.D.S.
per Sand Detector;
-
Data
Sheet, Inspection
D.S. per Sand Detector;
- Technical
Specific. e
R.D.D.S. for Fiscal Flow Measurement Daniel
Senior;
- Data
Sheet, Inspection
D.S. for Fiscal
Flow Measurement Daniel
Senior;
- Technical
Specification
e R.D.D.S. for Ultrasound Fiscal Flow Measurement;
- Data
Sheet, Inspection
D.S. or
Ultrasound Fiscal Flow Measurement;
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2008 |
Basis
Engineering
|
Rosetti
Marino |
Edina (Edison/INA) |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Izabela
North e South
Platforms
|
 |
Activity Description |
CAD drafting and revision of P&ID and Block Diagrams
retrieved from similar documents in electronic
format. The two agreed revisions performed have been
implemented according to the mark-up
and comments originated by Client over a PDF format copy of such
documents (got from the first drafting), and obvioulsy, together with
the relevant Client's personnel. |
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2008 |
Sogepi
|
N.A. |
Caffaro Torviscosa |
Italy |
 |
Industry |
Project |
Chemical - Biodiesel |
Impianto trasferimento olio grezzo e biodiesel
|
 |
Activity Description |
First drafting of instrumentation basic
engineering (almost detailed), to be related to plant for the transfer
of raw oils (incoming raw vegetables oils) and biodiesel
(as refined product), with pipelines between the marine terminal of S.
Giorgio di Nogaro (UD), and the refinery plant located in Torviscosa,
developed by another engineering company.
Prior
the drafting of mentioned engineering documentation, several
verifications
have been performed, including the comparison with another similar
plant
in an advanced stage of construction (Oxam - Oxon Energy of
Mezzana
Bigli - PV). Such verification session, together with the
analysis of available information, and on site inspections
(surveys both in Torviscosa and S. Giorgio di
Nogaro), for the portion of entrusted activities, has
immediately required:

- P&ID
verification for the instrumentation, control and
measurements aspect;
-
analysis, revision and new issue of Cause & Effects Diagram.
To
complete the entrusted activities, development
of instrumental
engineering (document drafting and subsequent revision), has
been performed, as follow:
common documents


-
Instrumentation General Specification for Pumping and Flow Metering
Station;
- Technical
Specification for Fiscal Flow Metering Systems;
- Instrument List for
Pumping and Flow Metering Station;
- Technical
Specification for On-Off Valves;
documents for marine terminal
- Instrument
List for Pumping
and Flow Metering Station;
- I/O List for Remote
Control System (DCS);
- Data Sheet
for Technical Flow Measurements;
- Data Sheet for Safety Valves (PSV-TSV);
- Data Sheet for Self Regulating Valves (FCV);
- Data Sheet
for Actuate Ball Valves;
- Data
Sheet
Actuated Valve Panels;
- Data
Sheet Pressure Switch;
- Data
Sheet
Temperature Transmitters;
-
Data Sheet
Pressure Transmitters;
-
Data Sheet Temperature Indicators;
-
Data Sheet Pressure Indicators;
biodiesel refinery plant
-
Instrument
List for Pumping
and Flow Metering Station;
- I/O List for Remote
Control System (DCS);
- Data Sheet
for Technical Flow Measurements;
- Data Sheet for Safety Valves (PSV-TSV);
- Data Sheet for Self Regulating Valves (FCV);
- Data Sheet
for Actuate Ball Valves;
- Data
Sheet
Actuated Valve Panels;
- Data
Sheet Pressure Switch;
- Data
Sheet
Temperature Transmitters;
-
Data Sheet
Pressure Transmitters;
-
Data Sheet Temperature Indicators;
-
Data Sheet Pressure Indicators.
|
|
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2008 |
Basis
Engineering
|
N.A. |
ENI Divisione
E&P |
Italy |
 |
Industry |
Project |
Oil
& Gas - Upstream |
Guendalina
Platform and Tea
Platform revamping
|
 |
Activity Description |
Development of several documents, both as CAD
drafting and revision services as also for detailed instrumental
engineering.

With
reference to performed CAD services, these can be listed as follow:

-
CAD drafting for Block
Diagrams;
-
CAD drafting for PFD
(Process Flow Diagrams);
- CAD drafting
for Material and Energy Balance;
- CAD drafting for P&ID;

in
a total context of three revisions (e.g. A, 0 and 1).
Subsequent revisions after the first, have been implemented according to the mark-up
and comments originated by Client over a PDF format copy of such
documents (got from the first drafting), and obvioulsy, in close
contact with
the relevant Client's personnel

Development
of detailed instrumental
engineering for Fiscal Flow Measurements (document drafting and
subsequent revision), as better
herebelow listed:

- Technical
Specification for
Fiscal Flow Measurement (Daniel
Senior);
- Data Sheet for
Fiscal Flow Measurement (Daniel
Senior);
- Inspection
Data Sheet for Fiscal Flow Measurement (Daniel Senior);
-
Technical
Specification for Ultrasound
Flow
Measurement;
- Data Sheet for
Ultrasound Flow Measurement;
- Inspection
Data Sheet for Ultrasound Flow Measurement;
|
 |
 |
Year |
Sub-Contractor |
Main Contractor |
Final Customer |
Location |
2007-09 |
Basis
Engineering
|
Rosetti
Marino |
Agip KCO |
Italy |
 |
Industry |
Project |
Oil
& Gas - Midstream |
Kashagan - Complex A & D Pig Trap
Skids
|
 |
Activity Description |
Development of detailed instrumental
engineering (document drafting and subsequent revisions), performed
both for specialized aspects, as also for required plant installations
documentation:
specialized instrumentation
- Supply
Specification per Actuated Valves and Valves Local Panels;
- Data
Sheet, Inspection
D.S. for ESV Actuated Valves;
- Data Sheet,
Inspection
D.S. for ESV Actuated
Valves Local Panels;
- Data Sheet,
Inspection
D.S. for Electrically Operated HS
Valves (MOV);
- Data Sheet, Inspection
D.S. e Supply
Specification for Pressure Transmitters;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Temperature Transmitters;
- Data Sheet, Inspection
D.S. e Supply
Specification for Flow Transmitters;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Orifices Plates;
- Data
Sheet, Inspection
D.S.
e Supply Specification
for Pressure Gauges;
-
Instrument List drafting and revision;
-
Valves List drafting and
revision;
plant installations
-
instrumentation bulk materials MTO;
-
Primary
and Secondary Hook-up
for Instrumentation;
- Electrical Hook-up for
Instrumentation;
-
Instruments
and Junction Boxes Layout;
-
Instrument Junction Boxes Terminations
drafting
and revision;
- Instrument Junction Boxes Rack Layout drafting
and revision;
- Instrument
and Air Distribution
Layout drafting;
- Instrumentation Cable Block
Diagrams revision;
-
Instrumentation Cable
List drafting
and revision;
-
Instrumentation Cable Routing Layout drafting
and revision;
-
Instrumentation Cables Technical Data
Sheet drafting
and revision;
-
Instrumentation Cable Tray Technical
Data Sheet drafting
and revision;

electrical, others
-
electrical materials MTO drafting
and revision;
- Electrical Cables Routing Layout revision;
-
instrumentation and electrical materials MIAP system
codification. |
 |
|
|
 |
|
 |
|
 |
|
|